Large-Format Bedplates for Turbogenerator Sets
We manufactured large, heavy-section bedplates and frames to support turbo-alternator equipment for the energy sector.

Project Data
In this project, the frame also incorporated a sealed oil tank, verified by pressure leak tests.
- Client
- Confidential
- End user
- Siemens Energy
- Sector
- Energy
- Year
- 2021-2026
- Market where it was implemented
- European Union
- What was manufactured
- 15 bedplates for turbogenerator sets
- Weight
- Between 16 and 24 tonnes per unit
- Dimensions
- Up to 12,000 × 4,000 × 1,000 mm; also units of 10,500 × 3,600 × 600 mm
- Project type
- Manufacture and painting
- Services provided
- Boilermaking, welding, machining, coatings and testing
The Customer's Need
Large, Strong Bedplates
The customer needed large, heavy-section bedplates capable of supporting its turbo-alternator equipment, for which it needed to hire a manufacturer with experience and technical knowledge of this type of structure, such as EPER Group.


The Challenge
Strict Geometric Control
The main challenge was to control the distortion inherent in welding a large-format, heavy-section structure, while also maintaining the tight geometric tolerances required for mounting the frame for the turbogenerator and, at the same time, ensuring the tightness of the oil tank integrated into the bedplate.
The Solution
Precise Manufacturing and Testing
We approached the manufacture of the bedplates with a combination of heavy boilermaking, welding, machining, coatings and testing, paying particular attention to the geometric control of a large-format, heavy-section structure.
The integrated oil tank was also validated through pressure leak tests, to ensure that the assembly met both the structural and the functional requirements of the equipment.


The Work Carried Out
A Recurring Project
The work was carried out as a recurring manufacturing project, active since 2021. Our work focused on the manufacture, testing and painting of the bedplates.
Thanks to the expertise of the EPER Group team, the specific requirements of the end customer were met, with rigorous manufacturing standards and testing to ensure the bedplates performed as required.
The Result
15 Bedplates with Sealed Oil Tanks
The final result was the manufacture and ongoing delivery of large-format bedplates for turbogenerator sets, weighing between 16 and 24 tonnes and built to demanding tolerances, which also incorporate a sealed oil tank validated by pressure tests.
Since 2021, we have delivered 15 units: an established solution for the ongoing manufacture of this type of industrial equipment.
Key Metrics
Key project data.
15 units
delivered with their final finish
Between 16 and 24 t
in weight
Up to 12 m
long
Gallery
Here is the manufacturing process behind these bedplates for turbogenerator sets.